Network Upgrade for Portion of our Terraform Runs
Complete

The scheduled maintenance has been completed.

Fri, Dec 21, 2018, 08:00 AM
(6 years ago)
·
Affected components

No components marked as affected

Updates

Complete

The scheduled maintenance has been completed.

Fri, Dec 21, 2018, 08:00 AM

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.

Fri, Dec 21, 2018, 04:00 AM(4 hours earlier)

Scheduled

Maintenance will begin as scheduled in 60 minutes.

Fri, Dec 21, 2018, 03:00 AM(1 hour earlier)

Scheduled

On Thursday, December 21th 2018 at 4:00 AM UTC, an upstream provider will be performing a planned switch upgrade to a pair of switches in their datacenter for approximately four hours. This upgrade could potentially cause some delays in Terraform Run processing and logging for a portion of our system.

Thu, Dec 20, 2018, 12:33 AM(1 day earlier)